Directional Drilling Insurance in New York

What New York law actually does to a fiber bore — a statute that names drilling and cables outright, splits enforcement between a commission and the Attorney General, and lifts both the penalty and the repair bill off a crew when the operator was the one at fault.

48 States Licensed
24+ Specialty Markets
§765(1)(b) When the Operator Erred
CPCU Led by a CPCU

New York is one of the few states where the damage prevention statute names the work a fiber crew does, names the plant it installs, and names the company that owns the line it might hit — all in the same set of definitions, and all without an analogy having to be drawn.

What follows is that statute and the Commission rules underneath it: where the notice window actually lives, the distance test that tells you when you may start, the penalty ceiling and who sues for it, the one provision that moves a repair bill back onto an operator, and the three-strike trigger that reaches a job rather than a license. Article 13 and Part 753 divide the paper from the fieldwork. The physics underneath both is described on the Directional Drilling Insurance pillar and the pollution liability page.

Boring in New York? One subsection can move both the penalty and the repair bill off a compliant crew.

Get a Free Quote

The definitions do the work before the duties start

Article 36 of the General Business Law is titled Protection of Underground Facilities, and its definitions section settles three questions a boring contractor would otherwise have to argue.

The work is named. Under §760(2), excavation means an operation for the purpose of movement or removal of earth, rock or other materials in or on the ground by use of mechanized equipment or by blasting, and it includes, but is not limited to, auguring, backfilling, drilling, grading, plowing in, pulling in, trenching and tunneling. Plowing in and pulling in are placement methods rather than digging methods, and their presence in the list tells you the drafters were thinking about linear plant.

The plant is named. Under §760(4), underground facilities means pipelines, conduits, ducts, cables, wires, manholes, vaults or other such facilities or their attachments installed underground by an operator to provide services or materials. Conduit, cable and wire are the three things a fiber build puts in the ground.

The counterparty is named. Under §760(6), an operator is a person operating underground facilities to furnish any of a listed set of services, and that list includes telephone or telegraph communications and cable television. The company whose line crosses your route carries statutory duties of its own, and the next section is why that matters more here than in most states.

The clock is not in the statute, and the band is narrow

Section 764(1) prohibits commencing any excavation until timely notice of the location and date is served on operators who maintain facilities in the area, and it provides that notice to a one-call notification system is deemed compliance — notice to the center is notice to each member. But the section does not say how long. It says notice shall be served in accordance with the rules and regulations adopted by the Public Service Commission under section 119-b of the Public Service Law.

Those rules are Code Rule 753. Under 16 NYCRR §753-3.1(a)(2), notice must be served at least two but not more than ten working days, not including the date of the call, before the commencement date of the excavation or demolition. Working days are Mondays through Fridays exclusive of public holidays.

Read both ends of that. Two working days is a short front end, and ten is a short back end. A ticket pulled at the start of planning is not merely early — it is outside the window for the date the schedule assumes, and it has to be pulled again. Crews that work several states in a season are the ones most likely to get this wrong, because the habit that is safe in a twelve-day state produces a void ticket here.

The rule does absorb ordinary slippage. Where an excavator postpones the commencement date for ten or less working days, no call to the one-call system or to operators is required; where the postponement runs more than ten working days, the notice requirements pertain again to the revised commencement date. Demolition carries its own separate step: under §753-3.1(c), at least seven working days in advance of a demolition commencement date the excavator must request a pre-demolition conference through the one-call system with all member operators having facilities at or near the area, and that request is expressly not a substitute for the notice of intent.

Fifteen feet, and the verification that is yours alone

Section 764(3) states the condition for starting work as a distance rather than as an elapsed time. An excavator may proceed if he has received notice from each operator notified by the one-call system either that it has no underground facility in or within fifteen feet of the proposed work area, or that the operator has marked any facility located in or within fifteen feet of it.

Marking is the operator’s act. Verification is not. Section 764(2) requires that, prior to any excavation, the excavator verify the precise location of the underground facilities in the manner set out in the Commission’s rules. The statute uses a different word for each party’s obligation, and a crew that treats a paint line as the end of the inquiry has performed the operator’s duty and not its own.

Section 764(4) then makes the markings themselves your responsibility to preserve: an excavator is responsible for protecting and preserving the staking, marking or other designation until it is no longer required for proper and safe work, for maintaining clearance between the facility and the cutting edge or point of any equipment, and for providing support to and preventing damage to any facility or its protective coating.

And if contact happens, §764(5) sequences the response and takes the repair decision away from you: the excavator must immediately notify the operator, no backfilling may be done until inspection or repairs have been made by the operator, and no repairs may be undertaken by the excavator until authorized by the operator. Where there is an electrical short or an escape of gas or hazardous fluids endangering life, the excavator must immediately notify the operator and 911, notify all persons who might be endangered, and assist in evacuation.

The Commission sizes it, the Attorney General sues for it

Section 765 splits enforcement in a way that changes how a matter should be handled from the first day.

The ceiling first. Under §765(1)(a), failure to comply with any provision of the Article subjects an excavator or an operator to a civil penalty of up to $4,375 for the first violation and up to an additional $17,500 for each succeeding violation occurring within a twelve month period. The twelve-month window is what makes the second number the one to plan against: a crew working a long route is exposed to the repeat tier for the rest of the year, not for the rest of the job.

Then the architecture. Under §765(1)(c), an action to recover a penalty is brought in the supreme court in the judicial district where the violation is alleged to have occurred, and it is commenced and prosecuted by the Attorney General. The Public Service Commission forwards its determination of the amount to the Attorney General, who may then commence the action, and money recovered is paid into the environmental protection fund. The body that sets the number and the body that comes to collect it are different, and the second one is a litigator.

Section 765(2) then forecloses the argument a contractor most often hopes for: except as otherwise provided in that subdivision, nothing in the Article impairs, limits or reduces the statutory, common law or contractual duties, or the tort or other liability, of any excavator working in the vicinity of underground facilities. Compliance with Article 36 is not a ceiling on what you owe anyone. It is a floor with a fine attached.

The subsection that moves the bill back

Most of Article 36 runs in one direction. Section 765(1)(b) runs in the other, and a boring contractor should be able to recite it.

The default is in §765(4): where, as a result of an excavator’s violation, an operator must make any repair to or provide new support to an underground facility, the excavator is liable to the operator for reasonable costs so incurred. That is the ordinary rule, and it is why a strike is usually an expensive event before any penalty is discussed.

Section 765(1)(b) removes both halves in one specific circumstance. The penalties provided for by the Article do not apply to an excavator who damages an underground facility due to the failure of the operator to comply with any of the provisions of the Article — and in such an instance the excavator is not liable for repairs as prescribed in subdivision four. Not a reduction, not an apportionment. The penalty does not apply and the repair liability does not attach.

Everything then turns on establishing that the operator’s non-compliance is what caused the damage — that the response to the ticket was absent, late, or wrong. That is a records question. The ticket and its timestamps, what came back from each operator and when, the photographs of what was and was not marked, and the measured relationship between the mark and the facility as found are the materials that make §765(1)(b) available. A crew that documents only its own care has assembled half of what this subsection asks for.

Three instances on one job

Section 765(3) gives an operator, or the Attorney General, a remedy that is not money. An excavator engaging in or proposing to engage in excavation or demolition in a negligent or unsafe manner which has resulted in or is likely to result in damage to underground facilities in such a manner that life, property or the continuation of operator service is endangered may be enjoined from that work, on application in supreme court in the county where the work is to take place.

The statute then supplies a threshold rather than leaving it to argument: three or more instances of damage by an excavator to underground facilities in the course of the entire self-same excavation or demolition activity are prima facie grounds for enjoining the excavator from further performance of that activity.

Note what that reaches. It is not a licensing action and it does not follow the company to its next job. It stops the work in front of it — which, on a long linear build with a schedule and liquidated damages behind it, is frequently the more expensive outcome. Three separate hits on one route is a threshold a busy crew can reach without ever having been found negligent by anyone.

The ticket that came back is the asset

The contractors who reach us in New York are usually mid-project, holding a certificate a prime has refused and an agent who cannot explain why re-issuing it will not help. In this state the more valuable document is the one the notification system sent back. Because §765(1)(b) can move both the penalty and the repair bill onto an operator that failed its own duties, and because §765(3) counts three instances against a single job rather than against a calendar year, what a crew recorded about each operator’s response decides more than any reissued certificate will. Ask what the operators returned, and when.

Pollution liability is the placement Article 36 never touches. The Article governs damage to facilities and the penalties for causing it; drilling fluid surfacing into a waterway or a wetland is an environmental loss the general liability form excludes, and it is not something §765(1)(b) can move onto anyone else. Contractors equipment matters because an injunction under §765(3) stops the work while the rig, the crew and the schedule keep costing money, and because the operator-fault relief addresses your liability to the operator and says nothing about your own machine. General liability is specified against the contract, for the reason set out immediately below.

Where §5-322.1 is clear, and where it stops

Unlike some states in this family, New York gives a contractor a good deal that is worth knowing before signature. It also has a limit, and the two should not be blurred together.

What is clear. General Obligations Law §5-322.1 voids a covenant, promise, agreement or understanding in, or collateral to, a contract relative to the construction, alteration, repair or maintenance of a building, structure, appurtenances and appliances including moving, demolition and excavating connected therewith, that purports to indemnify the promisee against liability for damage arising out of bodily injury or property damage contributed to, caused by or resulting from the negligence of the promisee, his agents or employees, or indemnitee — and it reaches that negligence whether such negligence be in whole or in part. That last phrase is the one to notice. Several states in this same family void only indemnity for the promisee’s sole negligence, which leaves a broad clause enforceable whenever the contractor is even minimally at fault. New York does not draw the line there.

The section also preserves the validity of any insurance contract, workers’ compensation agreement or other agreement issued by an admitted insurer — a qualifier worth reading, because it is doing work on a page about specialty placements. And it expressly does not preclude a promisee from requiring indemnification for damages caused by the negligence of a party other than the promisee, whether or not the promisor is partially negligent. So the statute voids the clause that shifts the promisee’s own negligence, and leaves standing the clause that shifts a third party’s.

Subdivision 2 adds something most anti-indemnity statutes do not. It voids a covenant purporting to condition a subcontractor’s or materialman’s right to file a claim or commence an action on a payment bond on the exhaustion of another legal remedy. For a fiber subcontractor on a bonded job, that provision is about getting paid rather than about getting sued, and it is void by statute rather than by negotiation.

Where it stops. What we cannot tell you is how the scope list applies to a fiber bore specifically. The list is written around a building, a structure, appurtenances and appliances, with excavating connected therewith. We have not located a New York decision construing that scope language as applied to utility, linear or fiber work, and we are not going to predict one for you. We could guess, and the guess would read like an answer — then you would set your retentions and your limits against something no court in this state has actually said. What is settled above is settled. The boundary question is open, and inside it your own contract is what governs.

Article 13 and Part 753 divide the paperwork from the fieldwork, and both halves are about one excavation. A contractor license, the New York markets and the other operating models are on our New York fiber contractor insurance page.

Why Fiber Optic Guard Insurance

What we actually do on a New York file: check that the ticket sits inside the two-to-ten working day band for the date the schedule actually assumes, because the habit from a longer-window state produces a void ticket here; build the locate record to evidence the operator side as well as your own, since §765(1)(b) is the only provision that moves a repair bill and it turns on the operator’s failure rather than your care; count instances against the job rather than the year, because §765(3) does; and read the subcontract against what §5-322.1 actually voids rather than against a general impression that New York protects subcontractors. If your contract carries a broad indemnity clause or a payment-bond condition, send it — both are provisions this statute speaks to directly.

Frequently asked questions about New York directional drilling insurance

Does New York’s damage prevention law cover buried fiber?

Twice over, and by two separate routes through the definitions. General Business Law §760(4) defines underground facilities as pipelines, conduits, ducts, cables, wires, manholes, vaults or other such facilities or their attachments installed underground by an operator to provide services or materials — cables and wires are named outright. Separately, §760(6) defines operator to include a person operating facilities to furnish telephone or telegraph communications or cable television. So the plant a fiber crew places and the plant it is most likely to strike are both inside Article 36, and the company that owns the line is an operator with duties of its own. The definition of excavation in §760(2) closes the loop from the other side: it expressly includes auguring, drilling, plowing in, pulling in, trenching and tunneling.

How much notice does New York require before a bore?

The Act itself does not carry the number, which is the first thing to understand about the New York clock. G.S. equivalents in other states put the window in the statute; here §764(1) requires timely notice served in accordance with the rules and regulations adopted by the Public Service Commission under section 119-b of the Public Service Law, and the window lives in those rules. Under 16 NYCRR §753-3.1(a)(2), notice must be served at least two but not more than ten working days, not including the date of the call, before the commencement date. Two working days is a short front end by national standards and ten is a short back end, so a New York ticket has a narrow usable band — pull it too early and it is void for the date you wanted.

What happens if I postpone a New York bore?

The rule distinguishes between a short slip and a real reschedule, and the dividing line is ten working days. Under 16 NYCRR §753-3.1, where an excavator postpones the commencement date for ten or less working days, no call to the one-call notification system or to operators is required. Where an excavator postpones more than ten working days, the same notice requirements pertain to the revised commencement date. For a crew sequencing around traffic control, permits or weather, that is a genuinely useful allowance — but it is bounded, and a route that slips twice can cross the line without anyone deciding to.

When can I actually start digging?

Section 764(3) gives the condition precisely, and it is stated as a distance rather than as a timer. An excavator may proceed with the work if he has received notice from each operator notified by the one-call system either that it has no underground facility in or within fifteen feet of the proposed work area, or that the operator marked any underground facility located in or within fifteen feet of the proposed work area. Fifteen feet is the operative radius. Separately, §764(2) requires the excavator to verify the precise location of the underground facilities before any excavation, in the manner set out in the Commission’s rules — marking and verification are treated as two different obligations, and the second one is yours.

Who imposes the penalty in New York, and how large is it?

The amount and the action come from two different places, which is the structural fact worth knowing before a matter starts. Under §765(1)(a), failure to comply with any provision of the Article subjects an excavator or an operator to a civil penalty of up to $4,375 for the first violation and up to an additional $17,500 for each succeeding violation occurring within a twelve month period. Under §765(1)(c), an action to recover a penalty is brought in the supreme court in the judicial district where the violation is alleged to have occurred, and it is commenced and prosecuted by the Attorney General. The Public Service Commission forwards to the Attorney General its determination of the amount, and on receipt the Attorney General may commence the action. Money recovered is paid into the environmental protection fund. The regulator sizes it; the state’s lawyer sues for it.

Is there anything I am not liable for in New York?

Yes, and it is one of the cleaner allocations in any state’s damage prevention statute. Section 765(1)(b) provides that the penalties under the Article do not apply to an excavator who damages an underground facility due to the failure of the operator to comply with any of the provisions of the Article, and that in such an instance the excavator is not liable for repairs as prescribed in subdivision four. Both halves matter. The default under §765(4) is that where an operator must repair or provide new support to a facility because of an excavator’s violation, the excavator is liable to the operator for reasonable costs incurred — so the ordinary rule is that you pay for the repair. Section 765(1)(b) removes both the penalty and that repair liability where the operator’s own non-compliance caused the damage. Proving which it was is a documentation problem, not a legal one.

Can a New York operator stop me from working?

It can ask a court to, and the statute tells you the threshold. Under §765(3), an excavator engaging in or proposing to engage in excavation or demolition in a negligent or unsafe manner which has resulted in or is likely to result in damage to underground facilities in such a manner that life, property or the continuation of operator service is endangered may be enjoined, on application of the operator owning the facilities or of the Attorney General, in supreme court in the county where the work is to take place. The statute then fixes a specific trigger: three or more instances of damage by an excavator to underground facilities in the course of the entire self-same excavation or demolition activity are prima facie grounds for enjoining the excavator from further performance. Three strikes on one job is not a rule of thumb in this state — it is written down, and it reaches the job rather than the license.

What does New York’s anti-indemnity statute do to my subcontract?

More than most states’ do, and the part we can state is worth stating precisely. General Obligations Law §5-322.1 voids a covenant relative to the construction, alteration, repair or maintenance of a building, structure, appurtenances and appliances including moving, demolition and excavating connected therewith, that purports to indemnify the promisee against liability for damage caused by the negligence of the promisee, his agents or employees, or indemnitee — and it reaches that negligence "whether such negligence be in whole or in part." That is broader than the sole-negligence line several other states draw. The section preserves the validity of any insurance contract, workers’ compensation agreement or other agreement issued by an admitted insurer, and it expressly does not preclude a promisee requiring indemnification for damages caused by the negligence of a party other than the promisee, whether or not the promisor is partially negligent. Subdivision 2 separately voids a clause conditioning a subcontractor’s or materialman’s right to file a claim or commence an action on a payment bond on exhaustion of another legal remedy. What we cannot tell you is how the scope list applies to a fiber bore specifically. We have not located a New York decision construing it as applied to utility, linear or fiber work, and we are not going to predict one.

Insure your New York bores on what the ticket came back with

Send the route, the ticket dates, and the subcontract. In New York the operator’s response is doing as much work as your own care is.